Construction
Start Date: 9/15/04, Move-in: 2/6/05, Open House: 2/20/05

There are more pictures than this: you can see them by date here.

Here is the architectural plan.

See pictures of Phase 2 of the construction project here.

 
9/11: BEFORE
  9/15: DAY 1: DIGGING THEIR WAY IN

 

9/15: DAY 1: DIGGING STARTS

 

 

9/22: DAY 7: TEARING OFF THE WALL


9/28: DAY 13: CONCRETE FORMS

 


10/5: DAY 20: CONCRETE POURED; FOUNDATION AND DECK FOOTINGS


10/14: DAY 29: FRAMING

 
11/1: DAY 47: LOOKING LIKE A BUILDING: OUTSIDE

11/1: DAY 47: INSIDE
 
11/6: DAY 52: WINDOWS

11/10: DAY 56: INTO THE HOUSE

 
11/14: DAY 60: DRYWALL

12/8: DAY 84: HARDWOOD FLOORS
  12/9: DAY 85: TILE STARTS

12/10: DAY 86: SHIMMING UP THE HOUSE
 
12/24: DAY 100: STUCCO

12/24: DAY 100: TILE PROGRESSES
 
12/30: DAY 106: PAINTING

1/5: DAY 111: LAUNDRY ROOM REWORK

 
1/5: DAY 111: DECK

1/8: DAY 114: FINAL VARNISHING
 
1/8: DAY 114: LOWER DECK COMPLETE

1/14: DAY 120: BATHROOM SHAPING UP

 
1/14: DAY 120: OTHER BATHROOM TOO

1/19: DAY 125: CLOSET ORGANIZER
 
1/19: DAY 125: EXTERIOR PAINTING

1/28: DAY 134: BATHROOM DONE
 
1/28: DAY 134: OTHER BATHROOM TOO

1/28: DAY 134: IT ALL COMES TOGETHER